February 26

Richmond-Dresden bridge work slowed by ice, but bridge could still open this year

The new bridge over the Kennebec River will take the place of a nearly 80-year-old deteriorating swing bridge used by 3,200 vehicles a day.

By Keith Edwards kedwards@centralmaine.com
Staff Writer

RICHMOND — Work on the new Richmond-Dresden bridge has been hampered by winter’s icy grip on the Kennebec River, but the contractor on the job still hopes to have it open to traffic in November this year.

click image to enlarge

TO THE TOP: Reed and Reed Inc. workers hoist rebar Wednesday to the top of pier five on the bridge the firm is building between Richmond and Dresden. Crews were installing the steel rods to reinforce concrete that will be poured inside the pier, which will support the deck of the bridge spanning the Kennebec River.

Staff photo by Andy Molloy

click image to enlarge

BLANKET COVERAGE: Reed and Reed Inc. workers unfurl a blanket Tuesday on the fifth pier of the bridge construction project between Dresden and Richmond. The top of the pier will be enclosed in the blanket so concrete can be poured into it while temperatures remain below freezing, workers said.

Staff photo by Andy Molloy

Fort Richmond dig site to be featured on National Geographic

RICHMOND — The Fort Richmond archaeological dig site and the Colburn House in Pittston will be featured in an upcoming episode of the National Geographic series “Diggers.”

The episode is scheduled to air at 10:30 p.m. March 11 on the National Geographic Channel.

In the episode, according to a summary posted on National Geographic’s website, the show’s hosts, history buffs George “KG” Wyant and Tim “Ringy” Saylor, visit the Fort Richmond dig site, searching for artifacts by using metal detectors.

The hosts and a film crew came to the dig before construction of the Richmond-Dresden bridge got underway last summer.

Promotional materials for the show say Wyant and Saylor were searching for artifacts related to Benedict Arnold’s stop at the Colburn House in Pittston when they got a call about Fort Richmond, and they learned the site was being paved over for use as a highway, so it would be “their last chance to free any artifacts from the ground.”

The pair, the materials say, uncovered an intact cannonball at the site, one of the rarest finds of their careers.

State archaeologists found hundreds of artifacts at the site.

The Fort Richmond site is also the setting for multiple “Diggers Blog” posts on the National Geographic website, with Bryan Cunning, supervising archaeologist for “Diggers,” discussing methods and tools archaeologists use in at least two video blogs shot at the Richmond dig site, with Route 197 visible in the background.

State archaeologists found parts of the original 1720s fort and the 1740s fort built to take its place, both at the same riverside Richmond site.

The road leading over the new bridge also will pass over the fort site.

That would put it well ahead of initial state Department of Transportation projections that the bridge would not be ready until July 2015.

Crews from Woolwich-based contractor Reed & Reed couldn’t finish as much work as they’d hoped on the concrete and steel piers that will hold the bridge surface when it is complete, because of the early, hard onset of winter.

“We’ve been struggling. The ice came early, froze up the river and seems to be holding really tight,” said Charlie Guerette, project engineer for Reed & Reed. “But we’re still working on the abutment on the Dresden side, and we’ll start on the Richmond side the first of next week. We’re still on schedule to begin setting structural steel in May. We’re pushing to get the new bridge open in November.”

Guerette said the contractor had hoped to work on the mid-river bridge piers until the middle of January, but the early freeze forced that work to stop around the end of December.

A crew of about 15 remains at the site, working on the parts of the project that can be done on, or near, shore. Come summer, when the deck is being built, more than 20 workers are expected to be working on the bridge.

For now, Reed & Reed’s barges and cranes are parked alongside the river, awaiting the ice’s departure.

The new bridge will take the place of a nearly 80-year-old deteriorating swing bridge.

The old bridge will remain in place and be used until the new bridge opens, then will be removed.

Guerette said Reed & Reed hopes to have traffic using the new bridge in November so its crews can spend next winter removing the old bridge.

Guerette thanked the public for its patience during the project, though with the old bridge available to use while the new one is built, delays for motorists have been few and far between.

One section of the rusted old green bridge swings to the side to allow taller ships to pass through. The new bridge is fixed, but it was designed to be tall enough to allow Coast Guard ice-breaking vessels to pass under it. At its peak, the new bridge will be 75 feet above the Kennebec River.

Guerette said the Coast Guard icebreakers will be able to get through the old bridge and the construction site for the new bridge to go upriver to break ice.

Reed & Reed won the bridge job with its $14.3 million bid and started working in July last year.

The new bridge is expected to cost about $18.6 million total, with engineering and construction costs included. The project initially was projected to cost as much as $25 million, but bids came in lower than expected, according to Ted Talbot, spokesman for the state transportation department.

In 2012 the bridge project was one of four nationwide designated to be fast-tracked through the federal We Can’t Wait initiative, which, federal authorities said at the time, could speed up the project by up to a year.

About 3,200 vehicles a day cross the old bridge, according to state data.

Keith Edwards — 621-5647 kedwards@centralmaine.com
Were you interviewed for this story? If so, please fill out our accuracy form

Send question/comment to the editors




Further Discussion

Here at OnlineSentinel.com we value our readers and are committed to growing our community by encouraging you to add to the discussion. To ensure conscientious dialogue we have implemented a strict no-bullying policy. To participate, you must follow our Terms of Use.

Questions about the article? Add them below and we’ll try to answer them or do a follow-up post as soon as we can. Technical problems? Email them to us with an exact description of the problem. Make sure to include:
  • Type of computer or mobile device your are using
  • Exact operating system and browser you are viewing the site on (TIP: You can easily determine your operating system here.)