December 10, 2013

Summit Natural Gas announces further, but shorter delays

Gas company says the project is still on track to lower heating costs for the Kennebec Valley over the course of the next few months.

By Rachel Ohm rohm@centralmaine.com
Staff Writer

WATERVILLE — Projected dates for when a pipeline will start delivering natural gas to area businesses and municipalities have changed, but officials from Summit Natural Gas of Maine say the $350 million project is still on track to reduce area heating costs in the next few months.

click image to enlarge

HERE’S THE DRILL: From inside a control building, operation engineer Terry Weber of Nomad Pipeline Services monitors the progress of a drill that is boring a 2,000-foot hole for a natural gas pipeline from Winslow under the Kennebec River to Waterville and Thomas College.

Staff photo by David Leaming

click image to enlarge

GOT GAS: Mike Earnest, left, founder and CEO of Summit Utilities Inc., and Mike Minkos, president of Summit Natural Gas of Maine, speak on Tuesday with Beth Gibbs, of Thomas College, at the school in Waterville before updating legislators and other officials on the status of the pipeline construction project.

Staff photo by David Leaming

Additional Photos Below

The company has contracts to deliver natural gas to about 500 area businesses in 17 communities in the Kennebec Valley, and it hopes its pipelines will deliver natural gas to Augusta and Hallowell in the next two weeks, said Mike Minkos, president of Summit Natural Gas, on Tuesday.

By early January, a regulator station in Randolph should be completed and service can begin to Gardiner; and by mid- to late January, the company anticipated it will be delivering to Waterville and communities to the north, Minkos said.

This is the second time officials from the company have said delays have caused them to push back projected dates for delivery of natural gas.

“It’s very difficult to explain the magnitude of a project like this. It’s a big undertaking, and it is not unusual to have problems or delays caused by the weather and other issues,” Minkos said.

The company has signed up more 1,400 customers, according to the company’s website, and expects to serve 15,000.

On Tuesday, officials from Summit as well as local and state leaders gathered at Thomas College, which this week announced a contract with the gas company to supply the college campus with natural gas.

The original schedule for the pipeline called for its completion in early November. In late November, a dispute with now-departed contractor Schmid Pipeline Construction Inc. of Mayville, Wis., caused some delays in Norridgewock and Randolph.

On Tuesday, Minkos said drilling is scheduled to resume in both locations this week.

Originally, the company had projected delivery of natural gas by Nov. 1 to Madison Paper Industries in Madison as well as several municipal and school buildings in Augusta and Gardiner.

In Gardiner-based Regional School Unit 11, officials had hoped to have natural gas from the pipeline by now at three schools in Gardiner, although the school district has not completed installation of natural gas burners that will be used in the new heating system, Superintendent Patricia Hopkins said. She said the district is expecting to have the burners installed and natural gas flowing by Jan. 1.

In Augusta, Ralph St. Pierre, finance director and assistant city manager, didn’t return a call for comment on Tuesday about when the city expected natural gas might be available to the Augusta City Center, Capital Area Technical Center and Buker Community Center. The Augusta School Department also did not return a call for comment on when gas might be available for Cony High School.

Summit officials said they expect to deliver natural gas to Augusta by the end of the month, although contracts between the city and Summit originally called for delivery to begin Nov.1.

In Waterville, an Inland Hospital spokeswoman earlier this month said the organization originally had expected to receive natural gas by mid-December, and other businesses north to Madison said they have been planning to receive natural gas in 2014 and expect there will be no further delays.

In the last 12 months, Summit has completed 100 miles of natural gas infrastructure, including 68 miles of steel transmission pipeline and 32 miles of distribution pipelines in Augusta, Fairfield, Gardiner, Hallowell, Madison, Randolph and Waterville, Minkos said.

“We’re here to give you gas, and we’re getting very close. The market is tremendous and natural gas is being welcomed here in the Kennebec Valley with great resolve,” Minkos said. He said the company has negotiated more than 1,500 contracts to supply natural gas, including a recent contract with Thomas College. The college announced earlier this week that natural gas would be part of a campuswide expansion plan that includes new investments in clean energy.

(Continued on page 2)

Were you interviewed for this story? If so, please fill out our accuracy form

Send question/comment to the editors


Additional Photos

click image to enlarge

UPDATE: Thomas College President Laurie Lachance speaks with Mike Earnest, founder and CEO of Summit Utilities Inc., on Tuesday.

Staff photo by David Leaming

  


Further Discussion

Here at OnlineSentinel.com we value our readers and are committed to growing our community by encouraging you to add to the discussion. To ensure conscientious dialogue we have implemented a strict no-bullying policy. To participate, you must follow our Terms of Use.

Questions about the article? Add them below and we’ll try to answer them or do a follow-up post as soon as we can. Technical problems? Email them to us with an exact description of the problem. Make sure to include:
  • Type of computer or mobile device your are using
  • Exact operating system and browser you are viewing the site on (TIP: You can easily determine your operating system here.)